Overview

NDT & Bridge Load Testing at GDR Lab

Existing structures raise a different question: not "will this material pass?" but "what is this member actually like now?" Non-destructive testing answers it without demolition — ultrasonic pulse velocity to find voids and honeycombing, rebound hammer for surface hardness, and cores where a measured strength is needed.

For bridges, we carry out load tests with the loading arrangement and deflection measurement set up so the recorded behaviour can be compared against what the design predicted, which is what an approving authority wants to see before a structure is opened or re-rated.

A rebound hammer test on a concrete column

What we test

  • Bridges and culverts
  • Beams, slabs, columns and footings
  • Industrial floors and water-retaining structures
  • Hardened concrete of unknown or disputed strength

Who this is for

  • Owners and authorities commissioning or re-rating bridges
  • Contractors asked to prove a questioned concrete pour
  • Structural consultants assessing existing buildings
  • Factories and plants checking structures before a change of use

Test list

10 tests, with the method for each

Need a test that is not listed, or a whole specification mapped to methods? Send us the schedule and we will come back with a quote.

Non-destructive testing of concrete

4 tests
  1. 01Ultrasonic pulse velocity (UPV)IS 13311 Part 1
  2. 02Rebound hammer surface hardnessIS 13311 Part 2
  3. 03Combined UPV and rebound hammer assessmentMethod on request
  4. 04Cover meter and rebar locationMethod on request

Semi-destructive

3 tests
  1. 01Concrete core cutting on siteIS 516
  2. 02Core compressive strength with correction factorsIS 516
  3. 03Carbonation depth assessmentMethod on request

Structural load testing

3 tests
  1. 01Bridge load test with deflection and recovery measurementIRC SP:51
  2. 02Load test on slabs and beamsMethod on request
  3. 03Instrumentation: dial gauges, deflectometers, levelsMethod on request

Methods are shown as commonly specified. The exact method, and whether a test sits inside our NABL scope of accreditation, is confirmed with your quote.

Where these tests are used

  • Commissioning or re-rating a bridge
  • Investigating a disputed or suspect concrete pour
  • Condition survey before repair or strengthening
  • Due diligence before a change of use or added load

Often combined with

Clients ordering ndt & bridge load testing usually also need

  • Building Materials & Mix Design

    Concrete mix design, cement, aggregates, concrete cubes, steel and bitumen.

    View tests
  • Site & Field Testing

    Geotechnical investigation, SPT, plate load, pile load and in-situ tests on your site.

    View tests
  • Rock Testing

    Strength and index properties of rock cores for foundations, tunnels and mining.

    View tests

FAQ

NDT & Bridge Load Testing: common questions

Can't find your answer? Ask us directly.

Can NDT alone tell me the concrete grade?

Not on its own. UPV and rebound hammer give you quality and uniformity, and they are strongest when read together across many points. Where a number has to be defended, we cut cores and test them, using the NDT readings to choose where.

What does a bridge load test involve on site?

A planned loading arrangement, instrumentation on the members being watched, and readings taken as load is applied, held and removed, so both deflection and recovery are recorded. It needs traffic control and the owner's permission, which we plan with you.

Do you work on buildings as well as bridges?

Yes. Condition surveys of beams, slabs, columns and industrial floors are routine work for this division, often together with core testing.

Need ndt & bridge load testing for your project?

Tell us the material and the tests; we reply within one working day.